Posted 27 September 2018
Category: Construction
From 1 September 2019, developers will no longer be able to obtain interim occupation certificates for buildings in NSW. This will likely complicate staged developments, as interim occupation certificates allow use of partially completed buildings.
Developers and builders should be aware of the impending changes and the legal ramifications.
A new building cannot be legally occupied without some certification that the building complies with the legal requirements and the building is suitable for occupation.
The Environmental Planning and Assessment Act 1979 (EP&A Act) provided for a process where occupation certificates can be issued by the Principal Certifying Authority.
Under the old section 109H(1) of the Act, reference was made to the two kinds of occupation certificates that could be issued by an authority:
The use of interim occupation certificates has been a controversial topic in the past. There was a lot of confusion about how interim occupation certificates could be used and what it means for a part of a building to be “partially complete”.
For instance, under the old regime, developers could “partially complete” one stage of a mixed use project and be issued an interim occupation certificate for occupation of the partially completed stage of the project. The developer could then move on and start work on another stage of the build without needing to comply with all the conditions of consent attached to the first stage.
This has led to scenarios where a staged building may have different statutory warranty periods, to reflect the different dates for the issue of interim and final occupation certificates.
The EP&A Act was amended earlier this year as a part of broad reforms to the state planning laws. The reforms removed all references to interim occupation certificates.
Section 6.10(1) of the EP&A Act (formerly section 109H(2)) provides that an occupation certificate must not be issued unless any preconditions to the issue of the certificate that are specified in a development consent have been complied with.
Previously, it was thought the regime would come into effect on 1 September this year.
The Government has recently made the Environmental Planning and Assessment (Savings, Transitional and Other Provisions) Regulation 2017 (Savings Regulation) to push back the proposed changes under the EP&A Act and developers have one more year to obtain interim occupation certificates.
The removal of the interim occupation certificates will have consequences for builders and developers alike:
Developers are still able to obtain interim occupation certificates under the saving provisions until 1 September 2019. However, given the notorious delays that can occur in the construction industry, builders and contractors should not assume that current projects will not be caught by the changes in legislation.
It is important that builders and developers are aware of the consequences of the changes in occupation certificates and anyone starting a new job should obtain advice about how the changes in occupation certificates could be factored into the project planning and contractual milestones.