Predicting the unpredictable: Strata Renewal in the Courts

Posted 02 May 2018

Category: Strata, Urban Renewal

Developers proposing projects involving strata renewal plans face a crystal ball gazing exercise. They need to predict the requirements and attitudes of the Court considering an application for orders implementing a strata renewal plan. The difficulty is the novelty of these applications, with little judicial guidance at this stage.

The Land and Environment Court has provided some guidance, including:

  • The Courtā€™s published practice note – Strata Schemes Development Proceedings (Practice Note).

These suggest that:

  • Owners supporting or opposing a strata renewal plan, i.e. supporting or dissident owners may, but need not be, joined as parties to the proceedings as respondents, the Court having given some guidance as to when and how this will occur.
  • A dissident owner who has become a respondent in proceedings must comply with the Courtā€™s practice requirements relating to provision of information relating to the respondentā€™s compensation claim.
  • Security for costs will not usually be awarded against the owners corporation in favour of supporting owners.
  • Security for costs may be awarded against the owners corporation in favour of dissident owners, especially if the owners corporationā€™s capacity to satisfy a costs order is in doubt, unless (as is likely) the need for this is displaced by the owners corporation entering into a deed with the proponent of the strata renewal plan, providing an indemnity with respect to costs payable to dissenting owners (and probably also the owners corporationā€™s own costs).

A number of big questions in respect of which we still await guidance from the Court include:

  • Whether the requirements, in Part 10 of the Strata Schemes Development Act 2015 (ā€œSSDAā€) that, in relation to a collective sale:
    • each owner receive ā€œcompensation valueā€ for the lot, representing ā€œmarket valueā€ and generally additional amounts, including ā€œrelocation costsā€; and
    • that the price payable for all lots be apportioned among lot owners in proportion to unit entitlements;

means that all lot owners receive the same relocation costs and additional amounts, whether or not they are appropriate.

  • How market value is to be determined for a lot, i.e. whether any premium value derived from selling all lots in the scheme to a developer is to be taken into account.
  • Further, whether any additional premium value derived from adjoining sites being held by or available to the developer is to be taken into account.
  • What ā€œjust and equitable in all the circumstancesā€ means in various scenarios, the Court needing to be satisfied that certain terms of the plan meet this requirement.
  • Further, whether the Court will look to what is ā€œjust and equitableā€ for owners supporting the plan or accept that the SSDA does not require this for supporting owners, who had the option of not supporting the plan.

There is still uncertainty in this area, which needs to be followed closely and needs further clarification from the Courts.

***The information contained in this article is general information only and not legal advice. The currency, accuracy and completeness of this article (and its contents) should be checked by obtaining independent legal advice before you take any action or otherwise rely upon its contents in any way.